Metronode Data Centre Silverwater

Project Location: 8-14 Egerton St, Silverwater

Company: Wilken Service Pty Ltd

Client : Metronode Pty Ltd

Complete: September 2013

Description:

Establish 2 x HVC units for the high voltage customer Metronode.

Excavate and install ducts and high voltage cable from Fariola Street to the customer’s premises in Egerton Street.

Supply, install and terminate customers high voltage consumer mains (2 sets of 11kV 300CuI triple x)